28th May 2010
South West Bypass
The final section of the £43M South West Bypass and the diversion of the canal at two-mile bend is complete.
Officially opened 25th May 2007
Contract Chemicals Site
Outline Planning Application submitted
5th April 2007
CEG “Outline planning application” approved January 2009 incorporating 15% on site affordable housing provision
Demolitions and site clearance commenced April 2009
A variation in the January 2009 consent conditions was approved in August 2009
Section 106 agreement awaiting completion following clarification of planning resolution at November planning committee
S106 Agreement still incomplete as at 18th May 2010.
Transco Site
An Independent report on the Transco site commissioned by the URC was presented to the National Grid 21st September 2007.
On 7th November National Grid responded and contested the findings of the URC consultants despite ‘in principle’ agreement on the proposed remediation strategy being obtained from the Environment Agency. To resolve matters, further technical work is to be commissioned to validate GHURC’s position.
Travis Perkins Site
Outline Planning Application approved for 142 residential development and associated infrastructure works on the former Monk Meadow Trading Estate 15 February 09
Bloor Homes
A re-plan of the development is expected due to the change in market conditions and demand. Re-plan application to follow with 4-storey canal side apartments being replaced by 2 and 3-storey townhouses. Overall unit numbers are likely to be reduced from 221 to 185.
A total of 100 new homes have completed up-to 31 March 2010